Register | Login
CASECHECK CASECHECK
CaseCheck(tm) Case Reports
Below are our most recent case summaries of Scottish Courts case reports, Employment Appeal Tribunal Decisions, Employment Tribunal decisions and House of Lords decisions. Please use the links on the left to access the case reports case summaries by case type. The CaseChecktm Scottish Courts,  Employment Tribunal summaries and House of Lords summaries can also be searched using our case reports search facility. The case reports search facility is available to registered users.
 
Where possible we have linked our case summaries to the corresponding judgment on the Scottish Courts Website or Bailii

**All information pertaining to the Scottish Courts Judgements remains the subject of crown copyright but may be reproduced without formal permission or charge for personal or in-house use.

Construction
Select Your Region: Scotland  England and Wales  UK  Northern Ireland  Europe  All
Selected Region: All
By Claire Adams on 02/02/2010 23:15
Supreme Court - Press Summary The Respondents, Barratt Homes Limited, were engaged in building a substantial development of homes and a primary school in Llanfoist, near Abergavenny in Monmouthshire. They sought to exercise the right of a property owner under s 106 Water Industry Act 1991 to connect the drains to the public sewer at a point close to the development. The appellant sewerage undertakers, Welsh Water, argued that it was entitled to insist on a connection at point some 300m furthe ...
By Law Brief Publishing on 02/02/2010 11:31
This case concerned a dispute about whether, as a result of an adjudicator’s failure to consider allegedly relevant evidence, he had breached the rules of natural justice and thereby rendered the subsequent award unenforceable. The Court held that it was within an adjudicator’s jurisdiction to decide what evidence was admissible and, indeed, what evidence was helpful and unhelpful in the determination of the dispute referred to him. Even if the adjudicator’s decision to disregard evidence as ina ...
By Law Brief Publishing on 02/02/2010 11:29
This case provides further guidance on the meaning of a “reasonable settlement” in cases where one party A seeks to recover from party C sums paid in a settlement to party B. The Court of Appeal held that because of its uncertainty and expense, prudent parties usually try to avoid litigation. The settlement value of a claim is not an objective fact but a matter of subjective opinion, taking into account all the variables. The Court only has to consider whether the settlement was within the range ...
By Law Brief Publishing on 29/12/2009 22:13
E, the contractor, was engaged to do works under a PPP contract with S the local authority. Following discovery of asbestos in the works, E claimed declarations that the works were delayed and that it was entitled to postponement of work plus a claim for compensation. However, the judge held that, pursuant to the clauses of the PPP contract, E had failed to give sufficient notice to S. Notice was agreed to be a condition precedent to the right of E to claim compensation or relief. Further, such ...
By Law Brief Publishing on 29/12/2009 22:11
The case concerned enforcement of an adjudicator’s decision where it was asserted by the resisting party, P, that there had been various issues referred that had not been in dispute at the time of the Notice of Adjudication. P, the employer, had given A, the contractor, a first notice indicating various aspects of work with which P was not satisfied. Following a second notice, P determined the contract and ejected A from site. The judge held that there had been a dispute about whether there were ...
By Law Brief Publishing on 29/12/2009 22:09
The case considered whether the defendant builder, K, had been in repudiatory breach of contract or, alternatively, whether termination of the construction contracts by the claimants, S and T, in itself constituted repudiatory conduct. K had agreed to carry out construction works at three properties owned by S or T (T being a director of S). S and T had purported to terminate the contracts by way of the K’s alleged repudiatory conduct, and which included delay and defects. K had transferred his ...
By Law Brief Publishing on 02/11/2009 10:24
In this Scottish case it was decided that a contractor who had been employed to construct a path leading to the top of some stairs on which the claimant fell was not liable for the loss suffered as a result of the fall. In 2004 the Health Board entered into a series of agreements with Impreglio relating to the construction and operating of a multi-storey car park in the grounds of the Glasgow Royal Infirmary. Impreglio in turn contracted with Laing to construct a path in the surrounds of the car ...
By Law Brief Publishing on 02/11/2009 10:22
Fitzroy were engaged as the architects for the development of three buildings in London and Buckinghamshire. The Fitzroy team assigned to the project was led by Mr Blake. However, whilst it was estimated that the project would take around three years, Mr Blake had in fact tendered his resignation before Fitzroy’s appointment was concluded. This meant that he was available to the project for no more than the first year. The Court found that Fitzroy did not tell the client that Mr Blake was le ...
By Law Brief Publishing on 02/11/2009 10:20
Costain was successful in establishing that Haswell had been negligent in the foundation design for a water treatment works. However, Costain failed in its claim for prolongation costs due to delay resulting from the need to redesign the foundations. Both programming experts agreed that some delay had occurred to the foundation works of the two structures due to the need to redesign. They also agreed that at the time of the delay, the foundation works were on the critical path of the project so ...
By Law Brief Publishing on 28/10/2009 11:04
Vision sought a declaration that the decision of an adjudicator was null and void for want of jurisdiction. Vision argued that the Scheme for Construction Contracts (England and Wales) Regulations 1998 provides that any request to a nominating body should follow the giving of a notice of adjudication. However, in the present case, Lancsville’s request to the nominating body had preceded the notice of adjudication. Vision argued that this invalidated the adjudicator’s decision. The Judge agreed. ...
1 2 3 4 5 6 7 8 9 10 ...
Bookmark and Share
Latest Jobs
Para-Legal, Aberdeen - An opportunity has arisen for a Paralegal in a well respected legal organisation in Aberdeen By Michael Page International (11/03/10) ... more

In House Litigation Lawyer, Edinburgh - Leading FS organisation is looking to appoint an in house litigation lawyer in Edinburgh to deal with arange of contentious work By Michael Page International (11/03/10) ... more

In-House Supply Chain, Aberdeen (AC09460) - International Oil and Gas Operator require a supply chain lawyer to join their dynamic team. You must possess previous supply chain experience from the oil and gas industry and this represents an excellent opportunity to progress. By Thorpe Molloy (04/03/10) ... more

Residential Property Solicitor, Aberdeen (AC09441) - Leading Aberdeen practice require an experienced residential property solicitor, ideally with a client following, to join their team. You must possess a strong background in residential property work, preferably in the Aberdeen area and there are excellent prospects on offer with this respected firm. By Thorpe Molloy (25/02/10) ... more

Oil and Gas Solicitor, Aberdeen (AC09444) - Leading national law firm currently require an additional oil and gas lawyer to operate from their Aberdeen office. You must possess previous upstream oil and gas experience and the role will involve working on a range of upstream oil and gas transactions for the firm’s extensive client base. Excellent long term career prospects on offer together with an attractive package. By Thorpe Molloy (25/02/10) ... more

Contentious Construction lawyer, Edinburgh - The role will involve all areas of contentious construction, and allow the successful candidate to become involved with business development and further client relationships. By Michael Page International (18/02/10) ... more

Interim In House Solicitor, Edinburgh - The role will involve all areas of investment management from assistance with product development and regulatory legal issues to general commercial legal drafting, negotiation and transactional work. By Michael Page International (11/02/10) ... more

Case Investigations Manager & Gateway Team Manager, Edinburgh - Scottish Legal Complaints Commission. We are looking for people with the vision, determination and drive to form a key part of our management team and lead our people, achieve objectives and play a central role in making a real impact for the people of Scotland. By Michael Page International (03/02/10) ... more

Employment Associate/Partner, Edinburgh - This is an excellent role for either a Senior Associate or a partner in an existing practice, covering both contentious and non contentious Employment matters, and potentially related issues. By Michael Page International (28/01/10) ... more

Commercial Property Solicitor, Aberdeen (AC09370) - Dynamic Aberdeen practice firm require a Commercial Property solicitor to supplement their existing team. By Thorpe Molloy (28/01/10) ... more

Show Articles Published:
Range From
Range From
 
CaseCheck Limited can be contacted at First Floor, George House, 36 North Hanover Street, Glasgow, G1 2AD, 0845 620 5664, info@casecheck.co.uk
CaseCheck(tm) is brought to you by CaseCheck Limited, Registered in Scotland No. SC325811.We take our job seriously and for this reason we respect your privacy, your data and the use you make of our site.   This work by CaseCheck Limited is licensed under a Creative Commons Attribution-Noncommercial-Share Alike 2.5 UK: Scotland License Creative Commons License. Please take a moment to read our legal notices: Disclaimer/Copyright Notice, Terms and Conditions, Privacy Policy.
This content is made available by CaseCheck Limited under a Creative Commons Licence