Case Summaries Up To September 2011
Select Your Region: Scotland  England and Wales  UK  Northern Ireland  Europe  All
Selected Region: All
By Law Brief Publishing on 07/09/2011 11:10
The claimant property owners sought to establish that the defendant builders (who had constructed the properties some eight years' previously) owed a duty of care in relation to physical damage to their houses. The roof to the row of terrace houses had been lifted by wind and dropped back onto the walls as a result of it not being strapped down properly. The defendants argued that there could be no liability because what was damaged was in essence "the thing itself". The court found in favour of ...
By Law Brief Publishing on 07/09/2011 11:08
Network Rail, the client defendant, succeeded in its application for summary judgment against parts of a claim brought by disappointed tenderer Mermec for alleged breach of the Utilities Contracts Regulations 2006 in the tender process for a track inspection system. Mermec alleged that the defendant failed to supply certain information about the bids meaning that Mermec could not make an informed decision within the standstill period as to whether to mount a challenge. Network Rail's argued that ...
By Law Brief Publishing on 06/09/2011 17:55
In an application for summary judgment to enforce an adjudicator's decision, the defendant argued that the adjudicator had acted in breach of the rules of natural justice by failing to notify the parties of the methodology that he proposed to use when calculating a value for the target cost under an agreement and the figures used for the purpose of making that calculation. The court held that the claimant was entitled to summary judgment in the sum claimed. The defendant had not demonstrated tha ...
By Law Brief Publishing on 28/07/2011 19:37
The court had to determine whether an adjudication agreement is capable of being repudiated and the legal position of a party who does not want to go ahead with the nominated adjudicator having instituted a reference to adjudication. The court had to decide whether, if the party abandons that reference, it can go ahead with another reference for the same dispute. The court held that under section 108 of the Housing Grants, Construction and Regeneration Act 1996, a party could not lose its right ...
By Law Brief Publishing on 28/07/2011 19:36
This was an application for summary judgment to enforce two decisions of an adjudicator in two separate actions brought against the respondent hotel owners. The court had to decide whether the adjudicator had failed to make a ruling on the defendant’s counterclaims and whether this amounted to a breach of the rules of natural justice. The court held that the question for the adjudicator was whether the counterclaims could be deployed as a defence to the claimant’s claims in the adjudication in t ...
By Emma Boffey on 22/05/2011 21:20
In this action, the petitioners sought judicial review of a decision of an adjudicator, who had adjudicated against them in a dispute with the first respondent. The petitioners and first respondent were engaged in a building contract for a house, which was only partially completed by the contractual end date. The petitioners withheld sums due under the contract on this basis. In response to this, the first respondent sought adjudication to determine the appropriate time extension to be awarded t ...
By Law Brief Publishing on 24/02/2011 23:00
The court was required to determine whether a defendant firm of solicitors was entitled to its costs on the indemnity basis. The court relied on the test set out in Excelsior Commercial & Industrial Holdings Ltd v Salisbury Hammer Aspden and Johnson (A Firm) [2002] EWCA Civ. 879, where the Court of Appeal reiterated that an order for indemnity costs could only be made where there was “some conduct or some circumstance which takes the case out of the norm.” The court stated that the exaggerated a ...
By Law Brief Publishing on 24/02/2011 22:59
The Claimant, CN Associates, applied for summary judgment to enforce the decision of an adjudicator. The issue for the court was whether the parties agreed to give the adjudicator jurisdiction to decide whether there was an effective construction contract in writing between the parties and, if not, as to whether there was such a contract between the parties. The court cited the well established rule that if a party does not effectively reserve its position on a given jurisdiction issue, of which ...
By Law Brief Publishing on 24/02/2011 22:58
Halo, a charity, sought to challenge the award of a contract for clearance of landmines by DFID to another charity, alleging breach of the Public Contract Regulations. The principal objection by Halo was that DFID had changed its policy, linking landmine clearance to other development activities, and that this had influenced the procurement process. The court said that the policy could not be challenged in this way; it would be a matter for a judicial review application. Halo also complained of ...
By Law Brief Publishing on 03/02/2011 22:40
The Defendant NHS Trust succeeded in its application for relief from the automatic suspension of its procurement process as a result of the Claimant tenderers’ challenge of its decision. The TCC described the case as raising issues as to how such suspensions should be treated, under the Public Contracts Regulations 2006 as amended by the Public Contracts (Amendment) Regulations 2009. The tender process was for establishment of a framework agreement for the operation of a purchasing function for ...
1 2 3 4 5 6 7 8 9 10 ...
 
This content is made available by CaseCheck Limited under a Creative Commons Licence  |  Terms Of Use