Case Summaries Up To June 2009
Select Your Region: Scotland  England and Wales  UK  Northern Ireland  Europe  All
Selected Region: All
By Law Brief Publishing on 25/06/2009 13:09
This case concerned a “pay when paid” clause. Such clauses are forbidden by section 113(1) of the Housing Grants Construction and Regeneration Act 1996 unless it can be shown that the third party employer is insolvent. Hare were engaged by Shepherd to fabricate and erect steelwork at a development in Wakefield. There was an express term of the contract, clause 32, which was in similar terms to the 1996 Act and defined the employer’s insolvency by reference to four alternate situations (1) an adm ...
By Law Brief Publishing on 15/05/2009 13:06
This case concerned pipelines drilled into an oil and gas reserve under property belonging to the claimant company (which was owned by Mohammed Al Fayed). The defendant had been granted a petroleum production licence under the Petroleum (Production) Act 1934. This permitted the defendant to drill down and extract the petroleum. The pipelines crossed the boundary of the claimant’s property at around 800 feet below the surface and terminated at between 2,300 and 2,800 feet. The Court held that the ...
By Law Brief Publishing on 27/04/2009 18:37
The claimant owned property which was damaged by an explosion caused by a gas leak. The leak was from a gas booster manufactured by the defendant. The defendant had been notified of three previous incidents in other premises involving boosters of the same design where the casing had cracked. After the third incident the defendant issued new product information notices advising regular inspection to ensure that the bearings supporting the shaft in the booster were in good condition. However, ...
By Law Brief Publishing on 08/04/2009 18:35
The claimants were civil engineers employed by the defendants to carry out construction work on highways in London. There was a final account dispute following completion of the work. Two adjudications followed. In the first, the adjudicator awarded £1.8 million to the claimant. In the second, the adjudicator made a declaration that the Sub Contract works, allowing for contra charges, should be valued at £23.3 million, requiring repayment of at least part of the award in the first adjudicati ...
By Law Brief Publishing on 13/03/2009 08:47
A property was built with defective foundations. The owner of the property claimed against the builder and the structural engineer who had advised on the depth of the foundations. The Court found that the structural engineer had been professionally negligent in respect of advice given about the required depth of the foundations. As a result, the builder had failed to build the house in accordance with NHBC Standards of Construction and was found to be in breach of contract and the Defective Prem ...
By Law Brief Publishing on 23/02/2009 10:53
The main contractor for the new Wembley Stadium (Brookfield, formerly Multiplex) attempted to rely on a clause requiring the Architect to give it access to its personnel so that it could carry out a fully and systematic review of the Architect’s services. The Architect refused; it argued that the operation of the clause ceased upon the completion of its services and argued that those services were already complete. Coulson J disagreed with the Architect. He found that the obligation continued af ...
By Law Brief Publishing on 17/02/2009 00:00
The Claimant claimed monies for installing electrical works at a house being built by the Defendant. The Claimant and the Defendant were friends. A figure of £15,000 was mentioned in discussions although little was put in writing. The Claimant then issued an invoice which stated that he would send the Defendant “a full job costing so that we don’t go over budget”. The dispute was whether the £15,000 was a figure agreed as a fixed price contract or whether it wa ...
By Law Brief Publishing on 04/02/2009 00:00
The Claimant had been successful in obtaining an adjudicator’s decision in its favour and applied for summary judgement, the sum not having been paid by the Defendant. However, the Claimant was subject to a company voluntary arrangement (“CVA”). The issue before the Court was whether the Claimant should be granted summary judgement or whether there should be a stay of enforcement because there were concerns that the Claimant would be unable to repay the sums awarded to i ...
By Law Brief Publishing on 28/01/2009 00:00
The Claimant, a contractor, made a summary judgement application for enforcement of an adjudicator’s decision. The Defendant agued that there was no crystallised dispute in relation to the claim because the claim was based on new expert evidence which had only been presented during the adjudication. Therefore, the Defendant argued, the adjudicator lacked jurisdiction. The Defendant also argued that the volume of new evidence was such that it did not have a fair opportunity to respon ...
By Law Brief Publishing on 21/01/2009 00:00
Dalkia sought a declaration under CPR Part 8 that the adjudicator to an ongoing adjudication between the parties lacked jurisdiction. Bell argued that the Part 8 proceedings were inappropriate because there was an issue of fact as to whether some of Dalkia’s terms and conditions were were received by Bell in April or May 2007. Coulson J stated that the TCC’s procedure should be flexible enough to avoid the result that one issue, in connection with an almost entirely irrelevant ...
1 2 3 4 5 6 7 8 9 10 ...
 
This content is made available by CaseCheck Limited under a Creative Commons Licence  |  Terms Of Use